Berlin - Gas, water and sewage installation works
Gas, water and sewage installation work (according to ATV DIN 18381)
Construction project: Berlin - New Museum of the 20th Century
Rainwater:
- Rainwater drainage from SML pipe DN80 to DN150 during construction
- 34 flat roof drains with drip trays made of titanium zinc
- Rainwater drainage from SML pipe and PE pipe DN50 to DN 200
- 22 wall penetrations DN80 to DN200
- Lifting system with approx. 47 m³/h
Dirty water:
- Drains: 4 string vents/ combi string vents, stainless steel drainage channel, 9 floor drains DN 100
- Waste water drainage: made of SML pipe, PE pipe, PP pipe and stainless steel (various nominal diameters)
- 1 underfloor lifting equipment and 10 free-standing lifting stations
Fettabwasser:
- Drainage channel and floor drains made of stainless steel
- Grease sewage pipe made of KML pipe DN 50 to DN 100, PE pipe DN 50 to DN 90
- Fettabscheinder NS7
- Lifting station with approx. 55 m³/h
Water systems:
- 2 water treatment modules consisting of a water softening system with downstream reverse osmosis system (each approx. 3,000 l/h); 1 water treatment module consisting of a water softening system with downstream reverse osmosis system (1,200 l/h)
- Various sanitary equipment for toilet areas (public and non-public), workshops, workrooms, changing rooms, showers and cleaning agent rooms
- Drinking water pipes (approx. 2600 m) made of stainless steel
- Various built-in parts and fittings
- Central water heating 1 piece by means of storage charging system; 2 pieces by means of flow system
- Decentralised water heating by means of instantaneous water heater
Other work
- Insulation and fire protection work ATV DIN 18421
- pipe heat
- core drilling
- Participation in commissioning management
In addition, the award of 'maintenance services' is the subject of the procedure.