Other electrical installation work | Tenderlake

Other electrical installation work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
15 March 2023
Closing Date:
12 April 2023
Location(s):
DE27B Ostallgäu (DE Germany/DEUTSCHLAND)
Description:
New primary school St. Martin in Marktoberdorf, building automation

The building automation system includes the control and monitoring of the complete MEP systems from the building. The services include the ASP cabinets, cabling up to the field devices and the connection to all necessary interfaces and components. All fault messages also occur in the building automation. The programming of the overall system and 1to1 tests are to be provided. One focus is the joint functional testing of all MEP systems.

KG 481

- Automation device / approx. 15 pieces / BACnet/IP

- Physical input/output / approx. 1,360 pieces / binary and analog input and output

- Object addressing of all addressable devices / 2,600 pieces

- Temperature, immersion temperature, air duct and room transmitter / approx. 260 pieces

- Optical signal transmitter CO2 traffic light / 41 pieces

- Field device signage / approx. 730 pieces / 30x70mm

KG482

- Control cabinet panels / approx. 40 pieces

- Power supply / approx. 30 pieces / 24VAC – 230VAC, 250VA – 400VA

- Power modules / approx. 60 pieces / 230V – 400V

KG 483

- Management operating function / approx. 5,830 pieces

- Hardware MBE / 3 pieces

KG 484

- Cable halogen-free / approx. 15,880 m / NHXMH-J, J-H(St)H

- Line HSLCH-JZ / 7.850 m / 4x1 - 7x1

- Electrical connection / approx. 1670 pieces

- Electrical plumbing pipe / approx. 275 m / 20mm – 25mm

- Junction box / approx. 340 pieces / 80/80mm

KG 485

-DIN rail mounting / approx. 40 pieces

- Patch and data cables / approx. 80 pieces

-Data cable Cat. 7a / approx. 1.000m / 4x2xAWG23

The building automation system includes the control and monitoring of the complete MEP systems from the building. The

Services include the ASP cabinets, cabling up to the field devices and the connection to all necessary

Interfaces and components. All fault messages also occur in the building automation. The

Programming of the overall system and 1to1 tests are to be provided. One focus is on the joint

Functional testing of all MEP systems.

Mass key data:

KG 481:

- Automation device / approx. 15 pieces / BACnet/IP

- Physical input/output / approx. 1,360 pieces / binary and analog input and output

- Object addressing of all addressable devices / 2,600 pieces

- Temperature, immersion temperature, air duct and room transmitter / approx. 260 pieces

- Optical signal transmitter CO2 traffic light / 41 pieces

- Field device signage / approx. 730 pieces / 30x70mm

KG 482:

- Control cabinet panels / approx. 40 pieces

- Power supply / approx. 30 pieces / 24VAC – 230VAC, 250VA – 400VA

- Power modules / approx. 60 pieces / 230V – 400V

KG 483:

- Management operating function / approx. 5,830 pieces

- Hardware MBE / 3 pieces

KG 484:

- Cable halogen-free / approx. 15,880 m / NHXMH-J, J-H(St)H

- Line HSLCH-JZ / 7.850 m / 4x1 - 7x1

- Electrical connection / approx. 1670 pieces

- Electrical plumbing pipe / approx. 275 m / 20mm – 25mm

- Junction box / approx. 340 pieces / 80/80mm

KG 485:

-DIN rail mounting / approx. 40 pieces

- Patch and data cables / approx. 80 pieces

- Data cable Cat. 7a / approx. 1.000m / 4x2xAWG23

Download full details as .pdf
The Buyer:
Stadt Marktoberdorf
CPV Code(s):
45317000 - Other electrical installation work