The services advertised with this specification include scaffolding work. The building is used with offices, seminar rooms and a multifunctional room as well as a shooting range and other special rooms. The lower and upper floors have an L-shaped floor plan with dimensions of approx. 63 x 16 or 21 m. On the ground floor there is a polygonal and not basement floor plan extension with a maximum of about 20 m opposite the lower and ground floor. The building envelope is designed as a perforated facade. The building complex, with a walk-flat roof above the ground floor and first floor, is partly built in cast-in-situ construction and a 30 cm curtain wall made of thermal insulation and fiber cement panels. or can be used to accelerate the shell work gem. static information all possible components are also erected as semi-finished parts.
The services advertised with this specification include scaffolding work. The building is used with offices, seminar rooms and a multifunctional room as well as a shooting range and other special rooms. The lower and upper floors have an L-shaped floor plan with dimensions of approx. 63 x 16 or 21 m. On the ground floor there is a polygonal and not basement floor plan extension with a maximum of about 20 m opposite the lower and ground floor. The building envelope is designed as a perforated facade. The building complex, with a walk-flat roof above the ground floor and first floor, is partly built in cast-in-situ construction and a 30 cm curtain wall made of thermal insulation and fiber cement panels. or can be used to accelerate the shell work gem. static information all possible components are also erected as semi-finished parts.
In total, a basement, a ground floor, an upper floor and a technical center are built in the DG.
Following the shell construction, the 4-storey building will be completely scaffolded.
The stand positions are done in sections and according to the different component heights
- from the EC, in approx. - 0,04 m under OKG to OK Attika EC cultivation, approx. 5,55 m as well
To Attica 1.OG, about 9.35 m as well
Until Attika staircase DG, about 12,85 m as well
Attica technical center, DG, about 14.35 m.
The facade scaffolding is placed at a distance of approx. 0.6 m to the outer edge of the shell wall. On the inside, 0.30 cm wide bracket extensions are to be mounted, which are to be dismantled in sections as part of the façade assembly.
Retention time beyond the basic working time of 4 weeks: 42 weeks
- about 300 m
- 150 m
- 2 200 m
- 405 m
- 1 100 m wall covering widening b = 0.30 m, build up, dismantle and hold,
- 2 200 m
- 2 200 m
- Prepare 1 st transport opening in the framework, 2 x 2 m,
- 47 m horizontal bridging, b = 4.00 m, installation height up to 8 m, set up, dismantle and hold,
- 65 m vertical lattice girder as stiffening, build, dismantle and hold,
- set up, dismantle and hold the 285 m roof scaffold on the outside console,
- 60 m
- 3 St. scaffold towers, LK 4 (3 KN / m
- install 77 m clamping flange on the awning construction made of steel profiles for the roof safety grille, installation height h = 3.80 m, dismantle and hold,
- 150 m³ interior scaffold, work scaffold, LK 4 (3 KN / m
- 235 m
- 4 pcs mobile work scaffolds, LK 3 (2KN / m
- 1 person and material lift, max. Load capacity 1500 kg, 3 stops, lift up to 12 m, set up, dismantle and hold,
- 1 ea. Corner scaffold tower, lxb = 3.00 x 2.75 m, connection lift / scaffolding bridge, build, dismantle and hold,
- 1-hour accessible ramp in the DG / connection to the scaffold bridge, inclination approx. 6%.