Project 22.823A/1 - Kortrijk, construction of DWA collector between the Bossuit-Kortrijk canal and Oudenaardsesteenweg
- FOLDER A: RIOLERINGSWERKEN
gresbuizen ø 250 mm, Ø 300 mm
Ongewapende betonbuizen ø 400 mm, ø 500 mm, ø 600 mm, ø 700 mm, ø 800 mm
Gewapende betonbuizen ø 400 mm, ø 500 mm, ø 800 mm, ø 1000 mm
PVC pipes Ø 400 mm
GVP tubes ø 500 mm
GRP tubes ø 600 mm
Concrete access and inspection pits: 75 pieces
Connections to the sewage system
construction of buffer moat with reinforcement by means of. posts and edge boards
cast iron street eddies
infiltratiestraatkolken
Related works
- LEAFLET B: ARTWORKS
overflow deposited on site: 7 pieces
Constructions poured on site: 2 pieces
head walls: 2 pieces
- LEAFLET C: ROAD WORKS
Breakdown of existing pavement
Asphalt Hardening
Cement concrete pavement
paving in concrete paving stones
Line-shaped elements
signalization
Related works
- LEAFLET D: LANDSCAPING
Construction of grass mats
Creation of herbaceous vegetation by seeding
Creation of herbaceous vegetation by planting with the exception of helmet
Creation of herbaceous vegetation by planting bulbous and tuber crops
Supplying and planting shrubs with bare root
Supplying and planting shrubs with root ball
Supply and planting of shrubs and climbing plants, in container
Supplying and planting of trees, with wire root ball
Related works and maintenance
Project 22.823A/1 - Kortrijk, construction of DWA collector between the Bossuit-Kortrijk canal and Oudenaardsesteenweg
- FOLDER A: RIOLERINGSWERKEN
gresbuizen ø 250 mm, Ø 300 mm
Ongewapende betonbuizen ø 400 mm, ø 500 mm, ø 600 mm, ø 700 mm, ø 800 mm
Gewapende betonbuizen ø 400 mm, ø 500 mm, ø 800 mm, ø 1000 mm
PVC pipes Ø 400 mm
GVP tubes ø 500 mm
GRP tubes ø 600 mm
Concrete access and inspection pits: 75 pieces
Connections to the sewage system
construction of buffer moat with reinforcement by means of. posts and edge boards
cast iron street eddies
infiltratiestraatkolken
Related works
- LEAFLET B: ARTWORKS
overflow deposited on site: 7 pieces
Constructions poured on site: 2 pieces
head walls: 2 pieces
- LEAFLET C: ROAD WORKS
Breakdown of existing pavement
Asphalt Hardening
Cement concrete pavement
paving in concrete paving stones
Line-shaped elements
signalization
Related works
- LEAFLET D: LANDSCAPING
Construction of grass mats
Creation of herbaceous vegetation by seeding
Creation of herbaceous vegetation by planting with the exception of helmet
Creation of herbaceous vegetation by planting bulbous and tuber crops
Supplying and planting shrubs with bare root
Supplying and planting shrubs with root ball
Supply and planting of shrubs and climbing plants, in container
Supplying and planting of trees, with wire root ball
Related works and maintenance