Measure no. 71047 E8 0002
PIZ 5325 New research building HuCaB
23E50141 Preliminary measure: Supply and disposal lines
23E50141 - PIZ 5325 Preliminary measure supply and disposal lines
site equipment
Traffic safety / control test
RW and SW sewer construction work
120 m KG 2000 DN 150
25 m KG 2000 DN 200
30 M BY 80 DA 160
230 M BY 80 DA 225
145 M BY 80 DA 355
20 m PE80 DA 560
Surface demolition and disposal work
Unbound base courses / subsoil improvement
Kontrollprüfungen
Rohrgrabenarbeiten
Crossings and underpasses
Receiving water, pipe penetrations and downspouts
Sewer and pipe demolition
Verpressarbeiten
Shaft demolition / disposal
Sewer and pipe demolition
drainage works
23 shafts according to the shaft data sheet
Partial renewal of the shaft
1 x Regenwasserpumpwerk T = 10,80
1 x Schmutzwasserpumpwerk T = 10,40
Rigolensystem
80 m Nahwärme KMR DN 80
Demolition and disposal work (OBerbau)
Leitungsgräben
Local heating pipeline in created trenches
Wasserversorgungsleitung
Demolition and disposal work
Oberflächenwiederherstellung