The services offered with this specification include the metal construction / steel construction work for the TGA headquarters on the roof 2OG, the canopies in the area ceiling above ground floor and the practice platform and all steel structures on the roof.
- 2,000 pcs. Mobile scaffolding terrain,
- 1,000 pcs. Mobile scaffolding roof,
- 600,000 m
- Build up 88,000 m stiffener with yoke beam
- 6,000 pcs cross beam HEB 280 grate TGA central, L 6425 mm,
- 14,00 St. Longitudinal beam HEA 100 Grating TGA central, different lengths,
- 3.315 m steel angle L 150 x 75 x 12 mm,
- 20,000 pcs. Position assurance, steel plate 150 x 50 x 10 mm,
- 5,500 m skirting h = 100 mm,
- 44.500 m substructure grating L 60 x 6,
- 95,000 m
- 29,000 St. HEA 240 "a" TGA center, L up to 5,000 mm,
- 2,000 St Wandverband Kreuzverband TGA Headquarters, Rd 16, Diag. L = 4.70 m,
- 11,000 cross beams HEB 240 "e" and "f" TGA control panel, L 6675 mm,
- 20,000 pcs cross beam HEA 120 "e" TGA central, L up to 3,000 mm,
- 30,000 pc. Longitudinal beam IPE 120 TGA central, L 2 670 mm,
- 8,000 St. Dachverband Kreuzverband TGA headquarters, Rd 12, Diag. L = 3.20 m,
- 138,00 St. substructure Attic QR 100 x 4 mm, L to 450 mm,
- 56,000 m
- 56,000 m
- 69,400 m substructure Attika U240,
- 220,00 m substructure facade sandwich panels U240,
- 8,000 pieces of lightning protection - Interception rods 170 x 40 x 10,
- 350,000 m
- 1.000 psch Vibration dynamic design,
- 43,000 pc. Support pedestal QR160x160x5, loose / fixed flange construction,
- 3,000 pc substructure exercise platform QR140 x 80 x 8, 4 475 x 2 100 mm,
- 3,000 pc substructure exercise platform QR140 x 80 x 8, 4 360 x 2 100 mm,
- 1,000 pc substructure exercise platform QR140 x 80 x 8, 4 540 x 2 100 mm,
- 1,000 pc substructure exercise platform QR140 x 80 x 8, 4 540 x 2 100 mm, double profile,
- 35.460 m substructure exercise platform QR 140 x 80 x 8, screwed,
- 194.83 m support concrete slabs steel angle L 120 x 120 x 10,
- 168,00 ea. Corner formation, bearing concrete slabs steel angle L 120 x 120 x 10,
- 34,000 pieces of support single-carrier,
- 9,000 pieces of deposit double-carrier,
- 1,854 m
- 78,000 m
- 30,000 m handrail exercise platform, round steel H 1,54 m,
- 5,800 m control beam HEB 240 canopy, L 2 900 mm,
- 37.700 m control beam HEA 240 canopy, L 2 900 mm,
- 16,100 m control beam HEA 240 canopy, L 4 500 mm,
- 17,400 m secondary beam IPE 160 canopy,
- 49,270 m secondary beam HEA 100 canopy,
- 11,000 m secondary beam HEA 120 canopy,
- 19,500 m secondary beam HEA 160 canopy,
- 7,850 m control beam HEA 240 canopy, L 7 850 mm,
- 89.100 m control beam HEA 500 canopy, L 9 900 mm,
- 24,000 pcs. Secondary beam IPE 200 canopy,
- 28,000 pcs. Secondary beam IPE 140 canopy,
- 4,000 m secondary beam HEA 140 canopy,
- 5,000 St. HEA 200 canopy, L 3 475 mm,
- 1,000 St. Wandverband Kreuzverband sleeve bearing, Rd 12, Diag. L = 4.65 m,
- 37.000 m control beam HEA 300 canopy, L 73 95 mm,
- 4,000 pcs. Secondary beam HEA 100 canopy, L 6,370 mm,
- 4,000 pcs. Secondary beam IPE 160 canopy, L 6 370 mm,
- 4,000 pcs. Secondary beam IPE 220 canopy, L 6,370 mm,
- 2,000 pcs. U-beam U 180 canopy, L 6,370 mm,
- 410.00 m