Work 1: tile work
- Subreport ELVIS ID E21157964.
Work 2: painting
- Subreport ELVIS ID E97631632.
Trade 3: Flooring work
- Subreport ELVIS ID E65644255.
Work 1: tile work
Execution in 3 separate construction phases (preliminary measures, 1st renovation section, 2nd renovation section)
- approx. 650 m
- approx. 450 m
- approx. 1 800 m
- approx. 650 m
- Approx. 100 wall mirrors as crystal mirrors in different sizes.
Work 2: painting
Execution in 3 separate construction phases (preliminary measures, 1st renovation section, 2nd renovation section)
- approx. 500 m
- approx. 7,000 m
- approx. 1,000 m
- approx. 18,000 m
- approx. 600 m
- Approx. 350 pieces of steel frame frames on the interior doors.
Trade 3: Flooring work
Execution in 3 separate construction phases (preliminary measures, 1st renovation section, 2nd renovation section)
- approx. 6,000 m
- approx. 6,000 m
- approx. 5 500 m skirting boards made of rubber flooring, mainly fillet skirting.