Agreement regarding contract work including earthworks/paving/electrical work at Kiruna Airport.
Retopping with mesh reinforcement of the runway and taxiways A and B, about 150,000 m2.
TWY A and the turnpike points at both ends of the runway will be widened in connection with the retopping, which means that ground and electrical work will also be required in addition to the actual retopping of the runway.
The contract also includes a number of other ground measures near the track, such as constructing an emergency road from the fire station, removing a number of old military road connections and parking areas adjacent to the track.
The contract will last during May-August 2024, of which the airport will be closed to air traffic w.29-30, during these weeks the contractor can work throughout the day, other weeks the work will be located during evening and night time.
General Contracted
Execution construction in accordance with AB04
Execution contract in accordance with AB 04, where the contractor shall act as general contractor.
Contract work includes, among other things;
Retopping with mesh reinforcement of the runway and taxiways A and B at Kiruna Airport, about 150,000 m2.
TWY A and the turnpike points at both ends of the track will be widened in connection with the retopping, which means that ground and electrical work will also be included.
The contract also includes a number of other ground measures near the track, such as constructing an emergency road from the fire station, removing a number of old military road connections and parking areas adjacent to the track.