The following special foundation engineering work is required:
- Ortbetonbohrpfahlwand DN 75cm ca. 890 m
- Bohrpfahlbewehrungskorb ca. 32 t
- Sheet pile PU 28 approx. 149 m²
- Sheet piling PU 18 approx. 1,450 m²
- Sheet piling PU 12 approx. 756 m²
- Schlossabdichtung ca. 2.350 m²
- Sheet piling approx. 2,347 m²
Dewatering:
- Lowering fountain 3 pieces
- Collection and drainage line approx. 225
The city of Memmingen, Stadtwerke Memingen, is planning the construction of a combined indoor and outdoor pool as a year-round pool.
The new building is to be realized on the site of the existing outdoor pool, after demolition of the existing one. The new combination pool includes a 25-metre swimming pool with 8 lanes, a diving facility 1 metre / 3 metre, a teaching pool with approx. 12.5 x 10 metres, a course pool with lifting floor, a toddler pool and other attractions. In the area of the outdoor pool, a 50-meter pool with 6 lanes, a non-swimmer pool with approx. 500 m² with various attractions and a toddler pool with approx. 100 m² will be built. In addition to a beach volleyball court, a playground and the like, an outbuilding with changing rooms, sanitary facilities and a kiosk will be built in the outdoor facilities.
For a detailed description of special foundation engineering and dewatering, see service description.
Scheduled schedule:
Start of work within 12 working days after receipt of the request, which is expected to be received by week 12/2023.
The service is to be completed (to be completed ready for acceptance) within 365 working days after the aforementioned deadline for the start of execution.