Installation services of electricity distribution equipment | Tenderlake

Installation services of electricity distribution equipment

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
15 December 2021
Closing Date:
17 January 2022
Location(s):
PL613 Bydgosko-Toruński (PL Poland/POLSKA)
Description:
Installation of photovoltaic installations in Zławieś Wielka Stage II

The subject of the contract is the implementation of the investment task entitled “Installation of photovoltaic installations in the territory of Zławieś Wielka Stage II”.

Detailed scope of work is included in Installation (Construction) Projects, in the relevant provisions of the contract, on the basis of Annex No 10 — list of installations and technical requirements — annex 11 (detailed description of the contract)

1. The subject of the contract is the implementation of the investment task entitled “Installation of photovoltaic installations in the territory of Zławieś Wielka Stage II”.

2. The scope includes:

The object of the order is the delivery, installation and commissioning of the installation of photovoltaic panels

in the places indicated in Annex 10 to the SIWZ on the basis of the design documentation and the guidelines of the Contracting Authority, implementation in Zławieś Wielka Municipality. The project will be implemented within the framework of the project “Installation of photovoltaic installations in Zławieś Wielka Stage II” within the framework of the Regional Operational Programme of the Kujawsko-Pomorskie Voivodeship for the years 2014 — 2020, Subaction 3.1 Supporting the generation and distribution of energy originating from renewable sources

The scope of the contract includes:

• the delivery of construction equipment and materials to the installation area necessary for the performance of the photovoltaic installation,

• execution in 80 facilities complete photovoltaic installations including the cooperating photovoltaic collector system automatically, inverter, necessary electrical installation,

Complete PV PV installation 3.06 kWp 6pcs.

Complete PV PV installation 4.08 kWp 15pcs.

Complete PV PV installation 5.1 kWp 56pcs.

Complete PV PV installation 9.18kWp 3pcs.

• filling of holes and restoration and repair of parts of damaged expeditions (finishing elements) during the execution of construction works,

• conducting tests of the entire installation and the necessary measurements,

• launch of the photovoltaic plant,

• development of instruction manual for photovoltaic installation,

• providing user instructions in Polish and informing them about the safe use of the photovoltaic installation,

• technical preparation of the installation and the submission by the owner of the property a correct application of the photovoltaic microplant with the relevant DSO.

2.1. Detailed scope of work is included in Installation Projects

2.1. Detailed scope of work is included in Installation (Construction) Projects, in the relevant provisions of the contract, on the basis of Annex No 10 — list of installations and technical requirements — annex 11 (detailed description of the contract)

2.2. Where a trade mark, patent or origin, source or specific process which characterizes products or services provided by a specific contractor has been indicated, the Contracting Authority shall allow the offering of materials or solutions' equivalent 'in terms of parameters technical, utility and operational provided that they guarantee the execution of works in accordance with construction projects and ensure that technical parameters are not inferior to those established in this SWZ and in the projects.

2.3. When describing the subject of the contract by reference to standards, European technical assessments, approvals, technical specifications and technical reference systems, the contracting agent shall allow equivalent solutions.

2.4. A Contractor who invokes the equivalent solutions described by the Ordering Party shall demonstrate that the supplies, services or works offered by him meet the requirements set by the Contracting Authority.

2.5. In the case of marking and certificates required in the construction project, the Ordering Party accepts the labels and certificates equivalent.

2.6. The required warranty period for works performed and for installed equipment calculated from the date of signing by the Contracting Authority of the Protocol for Receipt of the Final Investment Assignment (without observations) — shall be at least:

2.6.1.

• Photovoltaic panels — 12 years,

• PV panels for linear power warranty after 30 years 80%

• Inverter- min. 10 years,

• Works and other installed devices — min. 5 years.

OTHER CONDITIONS SET OUT IN THE SWZ

Download full details as .pdf
The Buyer:
Gmina Zławieś Wielka
CPV Code(s):
45261215 - Solar panel roof-covering work
45300000 - Building installation work
45311000 - Electrical wiring and fitting work
45311100 - Electrical wiring work
45311200 - Electrical fitting work
45312310 - Lightning-protection works
45315100 - Electrical engineering installation works
51112100 - Installation services of electricity distribution equipment
71314100 - Electrical services