Rehabilitation of 5 large concrete tanks
3 containers will be upgraded with PP sheet liner and 2 containers will receive tile lining.
BA2
Rehabilitation of 5 large concrete tanks:
- The bill of quantities includes the renovation of the container lining of the spa house.
- The concrete tanks are located in the 2nd basement in the technical cellar, which is accessible at ground level via a large insertion opening.
- The containers need to be sanitized. Access to the container is via a DN 800 manhole. A security post must be provided in the container for the duration of the assembly work and included in the unit prices.
- 3 containers will be upgraded with PP sheet lining and 2 containers will receive a tile lining.
- The foil container lining must be broken off and stored in a container provided by the client. The costs for disposal are borne by the client.
- Commissioning and instruction of operating personnel, preparation of audit and documentation documents