Brief description of the trades
Demolition and clearing work
(Paved and green areas to a small extent)
Erdaushubarbeiten
Reinforced concrete work, partly SB4
Steel construction work (on a small scale)
Stahlbetonfertigteilarbeiten
Insulation and waterproofing work
Masonry work
Erdungsanlagenarbeiten
Leerrohrverlegung
ground pipeline work
The Main-Taunus-Kreis intends to expand the Heinrich Böll School, Schulstraße 100 in Hattersheim am Main.
It is a school extension in the inner-city environment or on the outskirts of the city.
The school extension is being built on a school site that is currently in operation.
The following work must be performed:
Demolition and clearing work
(Paved and green areas to a small extent)
approx. 1.270 m2 Pflasterfläche
approx. 450 m2 of turf
earthwork
approx. 1.400 m3 Baugrubenaushub
approx. 1,710 m3 of excavated soil for media pipes
Reinforced concrete work, partly SB4
approx. 515 m3 of WU concrete floor slab, (strip) foundations, dragging beams
approx. 330 m2, d = 20-32 cm ceiling slabs reinforced concrete
ca. 770 m2, d = 24-32 cm Stahlbetonaußenwände
ca. 950 m2, d = 24 cm Stahlbetoninnenwände
approx. 100 m2 shaft walls
approx. 35 m3 columns, mainly inside
approx. 80 m3 beams and wall brackets
Steel construction work (on a small scale)
approx. 17.5 t HEB supports/beams
approx. 750 kg of section steel and small iron
Stahlbetonfertigteilarbeiten
10 pcs. precast concrete stairways
approx. 2,720 m2, d = 22-32 cm prestressed concrete hollow slabs
Insulation and waterproofing work
approx. 860 m2 of thermal insulation under foundation slabs
approx. 380 m2 of vertical perimeter insulation
approx. 95 m2 of PMBC waterproofing
approx. 1.230 m2 FBVF-Dichtungsfläche
Masonry work
approx. 360 m2, d = 24 cm masonry wall inside,
nichttragend
Erdungsanlagenarbeiten
approx. 380m ring and foundation earth with connection lugs
Leerrohrverlegung
approx. 460m Kunststoffrohr
ground pipeline work
approx. 70 m Grundleitungen
approx. 240 m sewage pipes
(dirty and rainwater)