Quantities:
- Lightning protection system class 3
- Approx. 2,300 m collection and discharges incl. roof line holder
- Ca. 2.400 m Ringerder
- Ca. 2.750 m Fundamenterder
- approx. 40 pcs. Air-termination rods
- Approx. 200 sqm mesh mats
incl. maintenance for 4 years
The city of Memmingen, Stadtwerke Memmingen, is planning the construction of a combined indoor and outdoor swimming pool as a year-round swimming pool at Stadtbadallee 3 (FlstNr. 3757/10, 3757/11 and 3747/3) in Memmingen. The entire building is designed and planned as a passive house. All construction structures meet the requirements of a passive house and are made in close coordination with building physics.
The new building is to be built on the site of the existing outdoor swimming pool, after demolition of the existing building. The new combined pool includes a 25-meter swimming pool with 8 lanes, a diving board 1 meter / 3 meter, a teaching pool with approx. 12.5 x 10 meters, a course pool with movable floor, a toddler pool, as well as other attractions.
In the area of the outdoor pool, a 50-meter pool with 6 lanes, a non-swimmer pool with approx. 500 m² with various attractions and a toddler pool with approx. 100 m² are being built. In addition, in addition to a beach volleyball court, a playground and the like, an outbuilding with changing rooms, sanitary areas and a kiosk will be built in the outdoor facilities.
For a detailed description of the trade to be created, see the service description.
Scheduled schedule:
Work will begin within 12 working days of receipt of the request, which is expected to take place in week 38/2023. The service must be completed (ready for acceptance) within 800 working days after the above-mentioned deadline for the start of execution.