The subject of the proceedings is the awarding of BIM management services for the project of new construction of the technical administration building in Düsseldorf. A step-by-step and, if necessary, section-by-section order is intended, there is no entitlement to further commissioning. The client is entitled to an ordinary right of termination at any time.
The subject of the proceedings is the awarding of BIM management services for the project of new construction of the technical administration building in Düsseldorf. Further information on the project can be found in the Council decisions and under www.duesseldorf.de/tvg.
The main features of the project are the following:
- New location for up to 3,000 employees
- Height approx. 110 m, 2 underground parking floors
- Implementation of a change process for the implementation of a new office space concept with desk sharing, introduction of the e-file and comprehensive digitization
- Comprehensive environmental sustainability goals, including:
- Certification DGNB-Platinum
- Gebäudebegrünung
- CO2-neutral design
- Application of the cradle-to-cradle principle
- Plus-energy house
- Integration of the traffic and tunnel control centre into the building (critical infrastructure)
- Metro station immediately adjacent
- The planning should be carried out fully with the BIM method
A step-by-step and, if necessary, section-by-section order is intended, there is no entitlement to further commissioning. The client is entitled to an ordinary right of termination at any time.