The locksmith and metal construction work for the practical part of the vocational school Höchstädt (in 2
Construction phases) consist of a circumferential Attika land and technical
Enclosures made of expanded metal on the roof surfaces of both construction phases, crash and
Fall-through protection made of frame with stainless steel nets on the roof terraces of the so-called
Wooden box, 2 large suspended canopies in front of the floor halls in BA1a and the
Stair railings, fall protection and handrails in two stairwells.
The building consists of a 3-storey structure (building height approx. 13.50 m =
BA 1a) with roof terrace and 2 staircases and a single-storey building with
publicly used roof terrace in BA 1b.
Short description:
The locksmith and metal construction work for the practical part of the vocational school Höchstädt (in 2
Construction phases) consist of a circumferential Attika land and technical
Enclosures made of expanded metal on the roof surfaces of both construction phases, crash and
Fall-through protection made of frame with stainless steel nets on the roof terraces of the so-called
Wooden box, 2 large suspended canopies in front of the floor halls in BA1a and the
Stair railings, fall protection and handrails in two stairwells.
The building consists of a 3-storey structure (building height approx. 13.50 m =
BA 1a) with roof terrace and 2 staircases and a single-storey building with
publicly used roof terrace in BA 1b.
masses:
- Attikageländer ca.290 lfm
- Enclosure technical areas approx. 120 m²
- Fall protection wooden box approx. 25 running meters
- Fall-through protection wooden box/floor hall approx. 25 m²
- 2 suspended canopy constructions (glass, steel, sun protection slats) approx. 130 m²
- Solid steel railing staircase 2 approx. 30m²
- Fall protection inside approx. 25m²
- Handrails made of stainless steel approx. 145 m
Events:
BA 1a: 3rd quarter 2023 (approx. week 27 to week 27)
BA1b: 1st/2nd quarter 2025 (approx. week 10 to week 14)