M As part of the Energetic Modernization of the component [KJF] of the Campus Handwerk of the Chamber of Crafts Hanover in Garbsen, the supply lines for gas, water and electricity are relocated outside the building in media trenches. These are to be led from the Trafohaus on the parking lot Seeweg 4, 30827 Garbsen according to the planning to the component [K] and branch off to the input component [F]. As well as a new water pipe from the component [A] to the technical room in the component [K]
Execution period 14.8-11.10.2019.
The tendered services include the laying of the new gas pipeline including all fittings and fittings. As well as the connection to paint booths:
- lay approx. 120 m of pipe in the created trench,
- conversion of the grid connection station,
- installation of the necessary fittings,
- ca 2 shut-off device in the soil,
- 2 building connections in the ground.