replacement of the current turbine, installed at the construction of the uiru, by a new Turbo Alternator Group to combine the production of electricity and the supply of thermal heat
- the studies necessary for carrying out its work and putting into service the new equipment installed, and for the design of the new ATM and its rackings,
- the decommissioning and decoupling of the existing ATM and its annexes for the integration of the new ATM into the existing water-steam cycle preserved,
- orders, supply and on-site delivery of equipment provided for in its market,
- the manufacture, works, development, overhaul and industrial commissioning of the new ATM and its annexes,
- training of plant operating staff