In the course of the general renovation of the primary, middle and open all-day school Goldbach, the outdoor facilities will also be adapted.
The content of BA1 is the first part of the landscaping work including locksmith and civil engineering work.
These include paved surfaces, two staircases, steps and two walls made of wall slices.
The delivery yard and the parking bay are produced as asphalt surfaces, mainly as a steep ramp with approx. 13%. The paving areas, the 3-step staircase with wall in the delivery yard are covered or / and only narrowly accessible.
Around the new building, the slope area will be remodelled and new lawn, flowering meadow and planting areas with a play combination and fall protection surface will be created. The finished area receives a new enclosure with bar fence and gate.
The locksmith work includes railings on existing wall slices, handrails and wide gratings.
Further equipment elements are 6 bench-table combinations, 2 trash cans, 2 umbrellas and a bench.
Landscaping work including locksmith work and civil engineering work
Stage 1:
- 250 m² concrete block paving, of which 115 m² decorative paving
- 190 m² Asphaltbeläge
- 90 m² Fallschutzbelag
- 1 staircase with railing 11 inclines with handrails
- 1 staircase 3 steps with handrail
- 6.5 m wall panels, 55cm to 1.3m
- 160 m³ floor application, application
- 110 m³ topsoil removal and application
- 280 m³ foundation excavation, trenches
- 350 m drainage, sewage pipes
- 10 m drainage channels
- 3 St Schachtabdeckungen
- 6 pcs point inlets (street and yard drains
- 66 m bar fence with a gate
- 16 m gratings with substructure for eaves stiffeners in front of escape doors (70cm wide)
- 32 m railing, of which 22 m stepped and inclined
- Equipment (play equipment, umbrellas, bench-table combinations, bench, waste)
- 345 m² Ansaatflächen
- 135 m² Pflanzflächen
5 pcs trees
- 480 m² completion maintenance 1 year