Construction work | Tenderlake

Construction work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
13 August 2021
Closing Date:
16 September 2021
Location(s):
DEA41 Bielefeld, Kreisfreie Stadt (DE Germany/DEUTSCHLAND)
Description:
L712, Bi/Brake-Bi/Old Ed., 4th BA. B61-L778, Lot 1: New construction Bw3 Milser Str and Neubau Bw () Milser Bach, preparatory work

Creation of two bridge structures - Bw 3 Milser Straße and Bw () Milser Bach.

Making a bypass of buildings on Milser Straße.

Route construction preparatory work, topsoil removal, construction road and deep drains L712. Later Milser Straße connects to the new bridge.

New building Bw 3 Milser Straße, 1-field building, surface area 385 m2

New building Bw () Milser Bach, frame structure made of prefabricated parts, superstructure area 100 m2

Bw 3 bypass, 1-lane traffic guidance with LZA

Route construction preparatory work, topsoil removal, construction road and deep drains L712

Litigation keeping work in the area of residential buildings Milser Straße

rerouting a private pressure pipeline

Later dismantling of the bypass, backfill and road connection Milser Str. to the new Bw

Quantities:

==============

a) Track construction

clearing up approx. 73,000 m2 of construction site

Absorb approx. 29,000 m3 topsoil, dispose

Produce approx. 1,220 m of leaping slot, 5m deep

Install approx. 17 units of inspection shafts DN 1,000

approx. 1600 m2 of FSS (0/45), make 50 cm thick

Absorb, conveying, installing approx. 850 m3 SoB

Carry out approx. 1,600 m2 soil improvement

produce approx. 1,300 m2 base layer AC 22 T N, 10 cm thick

approx. 1300 m2 top coat AC 11 D N, 4 cm thick, manufacture

approx. 1,300 m2 asphalt, 14 cm thick, milling, dispose

b) new building Bw 3 Milser Straße

1 psch techn. processing

1 psch construction site setup, clearance

ca.18.500m3 Produce excavation pit

filling approx. 425 m3 excavation pit

approx. 4,000m3 floor installation/backfill

approx. 105 pcs probing holes combat equipment

approx. 96 m2 of beam plank wall construction

approx. 45 m bored pile walls for construction

approx. 120 m2 sheet pile wall construction

500 m reinforced in-situ concrete piles diameter 120 cm, length approx. 15 to 18 m

approx. 160 m reinforced in-situ concrete piles diameter 120 cm, length approx. 7.00 m

1 psch load-bearing and working scaffolding

ca. 485 m3 concrete C 30/37 pile head beam

ca. 70 m3 concrete C 30/37 attachment shell

ca. 21 m3 concrete C 30/37 chamber walls

ca. 90 t rebar B 500 b

ca. 260 m3 concrete C 30/37 in-situ concrete slab beam superstructure

ca. 52 t rebar B 500 b

ca. 11 t tensioning steel 1570/1770

approx. 68 m3 concrete caps C 25/30 LP

ca. 8 t rebar B500 b caps

4 pcs elastomer bearings

approx. 15 m road crossing

approx. 54 m filling bar railing (h=1.30m)

approx. 54 m filling bar railing (h=1,00m)

approx. 410 m2 waterproofing layer made of waterproofing membrane

approx. 240 m2 mastic asphalt protection layer

c) New building Bw Milser Bach

1 psch techn. processing

1 psch construction site setup, clearance

produce approx. 700 m3 excavation pit

fill approx. 400 m3 excavation pit

ca. 27 m precast STB frame C 40/50

4 pcs. wing structures as prefabricated part (partly, in conjunction with frame element)

approx. 10 m3 reinforced concrete caps C 25/30 LP

ca. 27 t rebar B500 b (precast parts and caps)

approx. 30 m bar railing (h=1,00m)

approx. 110 m2 sealing layer made of waterproofing membrane

approx. 110 m2 concrete protection layer

Download full details as .pdf
The Buyer:
Regionalniederlassung Ostwestfalen-Lippe
CPV Code(s):
45000000 - Construction work
45221110 - Bridge construction work
45232453 - Drains construction work
45233120 - Road construction works
45233222 - Paving and asphalting works
45262210 - Foundation work
45262212 - Trench sheeting work