Work and testing on the 2 COMBANI boreholes is underway. The purpose of the consultation is to launch the work for their equipment and the installation of the discharge and conveyance pipes to supply the treated water tanks of the Miréréni plant
Topographic survey of the drilling site and others- topographical survey of the drilling site up to the Miréréni reservoirs- geotechnics of the built structures, drilling equipment- production of the pressurization tank and equipment for the inlet of the communal reservoir - remote management - supervision
Discharge line from borehole to tarpaulin and conveyance (1 of 3)the water network will be made of 200 mm cast iron. The works were divided into three homogeneous entities of about 1000 ml each
Water supply (2 of 3)the water network will be made of 200 mm cast iron. The works were divided into three homogeneous entities of about 1000 ml each
Water supply (3 of 3) with fordingthe water network will be made of 200 mm cast iron. The works were divided into three homogeneous entities of about 1000 ml each
Electricity and telecommunicationsElectricity and telecommunications