After completion of the first construction phase, the extension of the middle school (MS) is now taking place in a second construction phase, an increase in
of existing parts as well as supplementation of various areas and construction of a break hall between the new building, the gymnasium
and middle school. In addition, the collection of the middle school is to be completely refurbished. For this purpose, the building will be completely
cleared.
In the course of the renovation and expansion of the middle school in Germering, new tubular frame doors will be equipped with
built in fire safety requirements.
There are 32 door systems with different fire protection requirements from
T30 RS to T90 RS F30 and F90 glasses are also installed in this course, as well as ceiling detectors and
Mounted adhesive wall magnets for keeping open.
Events:
W+M planning: 28.02.22 — 21.03.2022
Start of assembly: 02.05.22
Completion: 7/15/22