The ZOP/ZSVA project is relatively centrally located on the Imland Klinik Rendsburg property. that
The building is being constructed as a 3-storey new building in conventional construction and is being experienced at the north and
east side, a direct connection to the stock.
To the east is the main building with the current operating room on the ground floor and the central sterilization in the basement
completion of the new building. The main traffic route will take place via this connection.
The adjoining parts of the building are retained in their static structure, and a conversion is primarily carried out in
Drywall.
9 pcs surgical lights
1 piece surgical light device