The NRW.URBAN GmbH hereby announces the building preparation / preparation as well as the construction of the waste water sewer for the Feldmark district.
The scope of the work includes the following main dimensions:
- approx. 85,000 m
- approx. 24,000 m
- approx. 37,000 m
- approx. 20,000 m
- approx. 3 400 t hydr. Deliver, distribute lime binder;
- approx. 1 900 t of biodegradable waste disposal;
- approx. 60,000 t disposal of excavated soil LAGA <= Z 1.1, <= Z 1.2, <= Z 2;
- approx. 11,000 t disposal of excavated soil> Z 2 landfill class <= DK 0, DK I;
- Deliver, lay approx. 320 m solid wall plastic pipe DN / OD 160, SN 12;
- Deliver approx. 740 m solid wall plastic pipe DN / OD 200, SN 12, lay;
- Deliver, lay approx. 310 m solid wall plastic pipe DN / OD 250, SN 12;
- Deliver and install approx. 30 shaft structures.
The NRW.URBAN GmbH hereby announces the building preparation / preparation as well as the construction of the waste water sewer for the Feldmark district.