For the BAB A45 in the maintenance section north of the Meinerzhagen valley from the Viaden valley bridge from km 68 + 768 to km 77 + 809, valley bridge Germinghausen, north of the AS Drolshagen, in FR Dortmund is a renewal of all lanes as well as the standing, edge, deceleration and acceleration ramps and interchange ramps for 2020/2021.
- about 24 780 m
- about 11 150 m
- about 66 000 m
- about 3 300 m
- peel about 23,000 m banquets,
- approx. 80,000 t disposal LAGA
- about 77 700 m
- about 83 300 m
- about 79 200 m
- about 122 000 m
- about 2 200 m
- produce approx. 58 800 m seam in the respective layer,
- produce about 43 900 m joints,
- Produce approx. 10 000 m of waterproofing
- break off about 6 500 m of shelf,
- make about 6 200 m shelves,
- about 50 m
- remove approx. 70 St.
- install approx. 50 St. street procedures,
- Make approx. 760 m connecting cables.
Amounts included for work in night construction sites
- About 1 560 m
- about 23 600 m
- about 11 800 m
- make approx. 5,000 m seam in the respective layer,
- make approx. 7 610 m joints,
- Produce approx. 1 400 m waterproofing edge.
- remove approx. 4 520 m ESP,
- remove about 3 520 m EDSP,
- dismantle about 3,970 m DDSP,
- dismantle about 720 m Super Rail,
- remove approx. 760 m concrete protection wall from in-situ concrete,
- produce approx. 80 m SR H2-W4-A,
- produce approx. 56 m SR H4b-W7-A,
- produce approx. 52 m SR Eco H2-W4-A,
- produce about 3 340 m SR Eco H2-W4-B,
- produce about 5 060 m EcoSafe / 2.0 H1-W4-A,
- produce approx. 40 m EcoSafe / 2.0 N2-W3-A,
- produce approx. 160 m EcoSafe / 1.33 H1-W3-A,
- produce approx. 120 m SR Eco BW H2-W1-B,
- make approx. 10 m SR Eco BW H2-W4-A,
- produce approx. 130 m SR Eco HS H2-W2-B,
- produce approx. 40 m SR Eco HS-BW H2-W1-B,
- make approx. 570 m SR Pro BW H4b-W2-B,
- produce approx. 1,200 m SR Eco MT H2-W4-A,
- produce approx. 2 510 m SR Eco 1a H2-W4-A,
- make about 1 310 m SR Eco double H2-W4-B,
- produce approx. 44 pieces ÜK,
- produce approx. 16 pieces ÜK ÜE,
- make about 14 AEK.
- produce approx. 11 350 m markings 0.15 m type I / II (continuous),
- make about 17 600 m markings 0.15 m type I / II,
(Dash 6 m / gap 12 m)
- produce approx. 70 m markings 0.15 m type I / II,
(Dash 3 m / gap 3 m)
- manufacture approx. 800 m markings 0.30 m type I / II,
(Dash 6 m / gap 6 m)
- make approx. 7 650 m markings 0.30 m Type I / II (continuous),
- produce approx. 220 m markings 0.50 m Type I / II as barrier markings,
- make approx. 40 m markings 0.25 m Type I / II as barrier markings (intersection of connection point),
- produce approx. 930 m markings 0.12 m type I / II (continuous),
- produce approx. 60 m markings 0.25 m type I / II (continuous),
- Make approx. 12 St. arrow markings type I / II.
- approx. 9 Psch traffic safety measures for construction phases with long-term jobs,
- approx. 10 Psch traffic safety measures for construction phase 8 with shorter working places (night construction sites),
- set up / dismantle approx. 31 000 m TSE T3-W4,
- set up / dismantle approx. 900 m tSE H1-W4,
- Produce approx. 60 000 m yellow marking film P7.
Mobile traffic jam warning system
The work in the tender specifications includes the following main services for a mobile traffic jam warning system:
- approx. 6 pc. LED display cross sections for installation in the side and median strip and operate,
- install and operate approx. 6 pc.
- 1 Psch, inter alia, obtain traffic regulations, provide and operate central and control units.