- About 1 100 m
- loosen, load and properly deposit approx. 500 t asphalt ring road (Alt),
- 1 750 m
- about 350 m
- deliver and install approx. 2 500 t frost protection layer,
- deliver and install approx. 1 000 t of gravel carrier layer grain size 0/32,
- about 2 200 m
- about 2 000 m
- deliver and lay approx. 50 m drainage pipe DN 150,
- about 8 St. street run 30/50 ran and install,
- deliver and set about 200 m high concrete curb
- approx. 100 m drainage channel, 3 rows of rectangular paving,
- 1 500 m
The traffic systems essentially comprise three sections. The construction of a paved ring road around the new building. The demolition and construction of a parking space with 72 parking spaces between the technical center and new building. The dismantling of the existing paved ring road in a partial area. The processing area of the new ring road including ancillary areas is approx. 3,000 m
The work Earthworks and superstructure of the ring road to asphalt base course and later the asphalt surface layer must be separated in time. The work Earthworks and superstructure of the ring road
Shall be done in the fall of 2019. The work on the asphalt surface course will be carried out in autumn 2020. In this meantime, the ring road is also for the
Construction site traffic can be used.