Site-development work | Tenderlake

Site-development work

Contract Value:
-
Notice Type:
Contract Notice
Published Date:
25 August 2020
Closing Date:
17 September 2020
Location(s):
DE126 Mannheim, Stadtkreis (DE Germany/DEUTSCHLAND)
Description:
External development Taylor construction phase 1 - earthworks and traffic route construction

The MWSP intends to renew the walking and cycling path "External development of the Taylor area, construction section 1".

The measure serves to develop the industrial park. To this end, the pedestrian and cycle path along the Spreewaldalle and Havellandstrasse is to be renewed, which will encompass the Taylor-West conversion area on two sides. The Spreewaldalle forms the eastern border for the entire Taylor area (Taylor-West development area with future Taylor Park).

MWSP Projektentwicklungsgesellschaft mbH, Robert-Funari Str. 32, 68309 Mannheim

Construction project "External development Taylor construction phase 1"

The work includes the following services:

- Existing sidewalks / lighting

- Earthworks approx. 1,600 m 3 ;

- Create the FSS / gravel base course approx. 1,600 m 3 ;

- Create a pavement approx. 260 m 2 ;

- Build on-board and channel systems approx. 2,700 m;

- Asphalt works approx. 4,000 m 2 ;

- Create green areas approx. 2,400 m 2 ;

- Create a bus stop with a tactile guidance system 3 pieces;

- Make lamp foundations 13 pieces.

Download full details as .pdf
The Buyer:
MWS Projektentwicklungsgesellschaft mbH
CPV Code(s):
45111291 - Site-development work
45112000 - Excavating and earthmoving work
45112200 - Soil-stripping work
45112210 - Topsoil-stripping work
45112310 - Infill work
45233252 - Surface work for streets