project management of the rehabilitation of 375 university studios - Cézeaux campus in Aubière
Market has 6 slices (1 farm and 5 optional)
project management works for the rehabilitation of 375 university studios
firm slice (building 21):
- Diagnosis: DIAG
- Preliminary project: APS and APD
- Project studies: PRO (request for administrative authorization (DP) to be made and deposit in the town hall, taking into account the criteria of the CEE-Bar or BAT sheets and the ERDF and Re2020 criteria
- Assistance to the client for the award of works contracts (Amt)
- Execution studies: Exe
- SSi (design phase)
- complete thermal study with before-after calculations
optional unit 1 (building 21):
- Direction of the execution of works contracts (Det)
- Assistance to the Client for the reception and the guarantee of perfect completion of the work (AOR)
- Piloting and Coordination Scheduling (OPC)
- ssi (execution and reception phases)
- diagnosis of energy performance after work
optional unit 2 (building 22):
- Diagnosis: DIAG
- Preliminary project: APS and APD
- Project studies: PRO (request for administrative authorization (DP) to be made and deposit in the town hall, taking into account the criteria of the CEE-Bar or BAT sheets and the ERDF and Re2020 criteria
- Assistance to the client for the award of works contracts (Amt)
- Execution studies: Exe
- Ssi (design phase) including creation or update of the Ssi folder
- complete thermal study with before-after calculations
optional unit 3 (building 22):
- Direction of the execution of works contracts (Det)
- Assistance to the Client for the reception and the guarantee of perfect completion of the work (AOR)
- Piloting and Coordination Scheduling (OPC)
- ssi (execution and reception phases) including creation or update of the Ssi folder
- diagnosis of energy performance after work
optional unit 4 (building 20):
- Diagnosis: DIAG
- Preliminary project: APS and APD
- Project studies: PRO (request for administrative authorization (DP) to be made and deposit in the town hall, taking into account the criteria of the CEE-Bar or BAT sheets and the ERDF and Re2020 criteria
- Assistance to the client for the award of works contracts (Amt)
- Execution studies: Exe
- SSi (design phase)
- complete thermal study with before-after calculations
optional unit 5 (building 20):
- Direction of the execution of works contracts (Det)
- Assistance to the Client for the reception and the guarantee of perfect completion of the work (AOR)
- Piloting and Coordination Scheduling (OPC)
- ssi (execution and reception phases) including creation or update of the Ssi folder
- diagnosis of energy performance after work