Geothermal project 19057 Schwerin-Lankow - laying of a brine line incl. ancillary systems (electric cables and conduits) for connecting two geothermal bores in Schwerin-Lankow
- laying of approx. 770m thermal water pipe SDR11 MF OT pipe 200/315
- laying of approx. 90m km pipe DN 300/500
- Installation of approx. 30m sewer pipe PP2000 SN8 DN 150
- laying of approx. 715 m cable protection pipes for fiber optic cables
in open ditch and controlled horizontal drilling process