The subject of the contract is the purchase of the section: construction, transfer and initial purification of the cullet. The section makes up an integral part of of the technological line for pre-treatment of the cullet.
The purchase of the section, construction, transfer and initial purification of the cullet:
1) Belt conveyors; 2) Belt scale with the tensioning station 2pcs; 3) Initial purification chamber 1 pcs; 4) Bucket conveyors 2 pcs; 5) Control cabin 1 pc.; 6) Cabin for compressors 1pc; 7) Steel structure weight 315 000 kg; 8) Hoppers cladded with 6mm sheets and lined with wear-resistant sheets, surface area 270 m2; 9) Sucking section with piping cladded with wear-resistant sheets; 10) Assembly of the technological line of total weight to 445 tons.