Oweninny Power 2 DAC, the contracting entity, is a joint venture company formed between Bord na Móna Energy Ltd and ESB Wind Development Ltd. Oweninny Power DAC has developed the first phase of a Wind Farm at Oweninny, Bellacorick, Co. Mayo. The contracting entity now intends to procure works, supplies and services related to electrical balance of plant (EBOP) for the Oweninny Phase 2 wind farm project.
Oweninny Phase 2 wind farm is an 83 MW project located adjacent to the existing 89 MW Oweninny Phase 1 project. The contracting entity plans to develop the phase 2 project commencing in 2020.
The contracting entity intends to procure works, supplies and services related to electrical balance of plant for the Oweninny Phase 2 wind farm project.
The scope of work for contract shall include the design, procurement and installation for the following non-exhaustive list, however tenders should note that the detailed scope and contracting strategy will be determined at tender stage:
1) EBOP civil works;
2) Earthing system for complete station and OEM plant areas;
3) Auxiliary power supplies;
4) Mechanical and electrical services;
5) Grid connection works – underground cable or overhead line as required;
6) HV end masts or cable connection terminations;
7) Grid transformer;
8) Neutral earthing resistor;
9) MV cable MV cable network;
10) MV switchgear MV switchgear;
11) Connection of Main LV and Standby supply;
12) Fibre optic cable network;
13) Control and protection as per employers specifications;
14) Connection to revenue metering;
15) Installation and wiring of OEM cabinets;
16) Installation and wiring of employers SCADA cabinets;
17) Studies if specified;
18) Design process and procedures;
19) Testing and commissioning;
20) Implementation of employers electrical transfer procedures including SAP;
21) Operations and maintenance requirements;
22) Permanent telecommunications for site;
23) Fulfilling role of PSCS or principal contractor during all or part of the Works, which may include other parties on site;
24) Met mast procurement and erection if required, including foundation and crane hardstanding.
Some post construction works/services during the project operational phase may also be included in the scope of the contract.