Construction of telecommunication cable conduits in the flush drilling process.
As part of the FTTH expansion in the district of Mecklenburg Lake District within 25 km around Neubrandenburg different local roads are to be produced in Spülbohrverfahren.
Mostly a pipe union with an outer diameter of 63 mm is to be pulled in. On certain sections of the route, a second RV of the same dimension shall be additionally drafted.
The tracks, each measuring at least 500 m to 6 000 m in length, are located along public transport routes and only outside built-up areas, so that the required start and finish pits are mainly to be made in unpaved surfaces along public roads.
The individual holes should be between 100 and 130 m long. Therefore, at least 4 holes per route are required.
The execution should start in KW 01 2020 and be completed at the latest in week 38 2020. Every week a realization of 2 400 m track length is to be ensured.