Gotha, Friedenstein Castle, west wing (ground floor, 1st floor + 2nd floor), west tower (2nd floor), dismantling/uncovering/securing work
Local dismantling of wall-mounted equipment and exposure of the supporting structure in sensitive areas of the castle, which must be carried out with the utmost caution
Gotha, Friedenstein Castle, west wing (ground floor, 1st floor + 2nd floor), west tower (2nd floor), dismantling/uncovering/securing work
Local dismantling of wall-mounted equipment and exposure of the supporting structure in sensitive areas of the castle, which must be carried out with the utmost care:
1 stair / load tower, h = 12 m, deliver + set up in the outdoor space
2 pcs makeshift stairs, h = 1.10-1.30 m, deliver + assemble
10 pcs rolling scaffolding, deliver + rearrange
500 m² foil / geotextile masking
Remove 272 m² concrete floor slab + cement screed with epoxy resin coating + dispose of
Remove 272 m² of polystyrene + dispose of it
292 m² gravel / base course, d = 10 cm, remove + dispose of
18 m² sandstone floor slabs, h = 10 cm, pick up + store
16 pcs Removing + disposing of night storage heaters
Drill out + dispose of 100 small iron parts
Create 20 search cuts in the wall plaster, 20-50 cm x 20-50 cm
Remove + dispose of 370 m² of wall plaster on MW
Remove + dispose of 240 m² of wall plaster on half-timbered walls
Remove + dispose of 52 m² compartments in half-timbered walls
Dismantle + dispose of 40 m² HWL panels with batten construction
Remove + dispose of 12 m² wall tiles
Remove + store 75 door leaves from the 18th/19th century
Remove + store 10 18th/19th century door linings
7 pcs remove doors + dispose of them
Remove 5 pcs door chuck + dispose of
Dismantle + dispose of 41 m² drywall/timber stud walls
Pick up 73 m² of historic oak parquet flooring + store it
585 m² plank / with bearing timber pick up + dispose of
34 m² hist. Picking up and storing floorboards
Pick up 38 m² dry screed + dispose of it
Remove 10 m² linoleum + dispose of it
Pick up + dispose of 150 m² gypsum/anhydrite screed
Pick up + dispose of 325 m² of modern parquet flooring
73 m² of blind floor pick up + dispose of
1,037 m Pick up + dispose of levelling floor timber 4-20/6-22 cm
140 m² half-timbered walls, b = 18-22 cm, dismantle + dispose
30 m³ beam of timber, softwood, S7, for construction aids (support of ceilings)
Remove 435 m² of ceiling plaster + dispose of it
Remove 600 m ceiling stucco profile + dispose of it
18 pcs Exposing window lintel reveal (plaster, carrier plate) Remove + store, partly dispose of
Remove 10 m² vaulted plaster in small parts + dispose of it
Exposing 60 m of beams (plaster removal + disposal)
Remove 270 m² ceiling partitions + dispose of them
Remove + dispose of 270 m² of staked timber
Pick up 150 m² of fill + dispose of it
25 m² mineral wool, d = 10-20 cm, remove + dispose of
355 m Exposure of wall base truss walls in the ground, b = 80 cm, disposal of finishing materials: fill, storage timber)
3.6 m³ dismantling + re-masonry quarry stone MW
Bricking 8 m² compartments
Remove 5 pieces of masonry from former passages + dispose of them
Supply + install 1,020 m² of wood-based panels
Laying 290 m² of wood-based panels
3 m³ joinery of ceiling beam heads, interchangeable beams, half-timbered timber in traditional carpentry, coniferous wood
0.6 m³ Joinery of wall sleepers in traditional carpentry, oak
90 fittings for truss and ceiling beam constructions supply + use
44 m steel supports HEB 100-240 or HEA 100-280 deliver + install
425 m² of wall/column cladding (plaster, HWL, batten construction) dismantle + dispose of