Tile work 1_BA
Brief description of the measure:
On the site of IGS Lindenfeld, a 3-storey extension for a primary school is to be built next to the existing main building. The construction project will be carried out in 2 construction phases. The service described here concerns the 1st construction phase.
Further descriptions: see bill of quantities
Execution times:
Technical clarification, sample: within 4 weeks after placing the order
Waterproofing walls: 12.02. - 16.02.2024
Wall tiles: 19.02. - 01.03.2024
Floor tiles: 18.03. - 15.04.2024
Main positions
Waterproofing walls 250sqm
Wall tiles 15/15cm 250sqm
Waterproofing floor 120sqm
Floor tiles 30/30cm 120sqm
Floor tiles 30/60cm 205sqm,
Staircase tiles 1-run and 2-flight staircase over 2 floors