RV crash barrier repair 2024 to 2026, framework contract crash barrier repair area AM Döbeln + AM Leipzig
Traffic safety
500 pcs traffic safety shorter duration day
20 hours traffic safety shorter duration at night
45 hours closures at junctions and PWC systems
Mining and manufacturing FRS
1700 m ESP
2800 m EDSP + EDSP Bw
200 m DDSP
3200 m Super-Rail + Super-Rail Bw
40 m Super-Rail Plus Bw
20 m Super-Rail HS
20 m Super-Rail double
300 m SR Eco + Super Rail Eco Bw
40 m SR Eco MÜF
200 m SR Eco HS + Super Rail HS BW
20 m SR Eco double
80 m Mega Rail s
40 m Mega Rail sk
20 m Mega Rail bw
3000 m Eco-Safe + Eco Safe Bw
40 m Easy-Rail
40 m Mega Rail sl
100 units between existing FRS systems
Dismantling and manufacturing 75 pcs anchors
Since this contract is a framework agreement, the quantities quoted are estimates based on the experience of the last two years. The contract period is 24 months with the one-time option to extend it for 6 months.
The maximum order value is the actual order amount + 10%. There may be deviations during the year and an adjustment may be necessary. A claim of the contractor (contractor) to the tendered quantities is excluded.