Expansion of the administrative site of the Görlitz District Office - Lot 10-N Shell construction work
earthwork
• 1,800 m³ excavation work Foundation of single, strip, slab foundations
• Install 1,650 m³ gravel 2/45
• 4.400 m³ Bauwerksrückverfüllung
Sewer works
• 375 m³ Rohgraben
• 250 m canal and various shafts
concrete work
• 350 m³ Streifenfundamente
• 685 m³ Einzelfundamente
• 800 m² floor tiles
• 2 Aufzugsschächte
• 2,900 m² StB walls partly SB2
• 300 STB supports up to C45/55
• 11,000 m² ceilings up to C45/55
• 800 t structural steel
Bricklaying
• 360 m² KS 2DF exposed masonry
grounding system
• 6,800 m steel strip
• 3.400 St Verbindungsklemmen
• 3,600 m V4A round