Kuopion Electrogrid Oy (KSV) will build a new 110 kV substation as a KVR acquisition. The old existing air-insulated switch plant will be replaced by a new GIS type switch plant during 2022-2023. The new 110kV GIS switching equipment will be placed in a new separately constructed instrument building next to the existing 20/10 kV instrument building. The old open switch field will later be dismantled in a separate chore.
The acquisition is described in more detail in the Appendix of the Project Description Savilahti GIS.
Delivery includes a 110 kV GIS instrument set in the new instrument hall with peripherals.
The new Savilahti substation will be connected to the 110 kV tire network in Kuopio Electricity network using cables. 110 kV cabling works and cables are not part of the chore. 110 kV cabling is acquired as a separate chore.
KJ cabling between an existing 20/10 kV instrument hall and the new 110 kV instrument hall is not part of the chore.
KJ cabling is acquired as a separate chore.
The contents of the delivery are described in more detail Project Description in the Savilahti GIS Annex.