The current Fillan school, 1st - 10th classes, consists of buildings that were constructed in various building stages, wherein the oldest part is from the end of the 1960s and the newest is from 2007. The municipal administration has decided on a step-by-step construction of the new Fillan school for approx. 330 pupils. In connection with this, the contracting authority would like to enter into a contract with a tenderer as a turnkey contract with interaction for the development and construction of the new school.
The procurement consists of the following:
1. Design and development of the new school in an interaction phase (Phase 1 – development phase)
2. Detailed engineering design and construction of the school (Phase 2 – implementation phase)
Click here: https://permalink.mercell.com/196210405.aspx
The current Fillan school, 1st - 10th classes, consists of buildings that were constructed in various building stages, wherein the oldest part is from the end of the 1960s and the newest is from 2007. The municipal administration has decided on a step-by-step construction of the new Fillan school for approx. 330 pupils. In connection with this, the contracting authority would like to enter into a contract with a tenderer as a turnkey contract with interaction for the development and construction of the new school.
The procurement consists of the following:
1. Design and development of the new school in an interaction phase (Phase 1 – development phase)
2. Detailed engineering design and construction of the school (Phase 2 – implementation phase)
The project will be executed in two phases:
- Phase 1 will be a joint planning and development phase where the parties shall, among other things, carry out investigation work, design work and engineering design. Furthermore, progress plans, risk registers and target sums for the project must be prepared, as well as supplementary contract documents for phase 2 - implementation phase.
- Phase 2 includes detailed engineering design, work start-up and completion of the physical measures at the building site.
The project must be carried out in close cooperation with key persons at the contracting authority and other hired resources in the project. This will include, possibly among other things, the contracting authority's project management, user groups, and the political environment.
A more detailed description of the delivery and the collaboration contract follows from the collaboration agreement with annexes