Ready-to-use production of approx. 660 meters of a district heating line in Karlsruhe, Knielingen district.
The contract includes the conventional grouting of the Raffineriestraße over a length of approx. 42 m, civil engineering and pipeline construction work as well as the restoration of the surface.
Pipe material Plastic jacket pipe DN 350/520 is provided by the client. Pipes for MSR technology must also be laid; Delivery also on site.
District heating extraction Stora Enso Lot 2Lot 2 comprises approx. 462 m of route.
Beginning and course of the route: The route of lot 2 starts in the street Am Kirchtal north of the B10 and initially runs approx. 160 m to the north.
At the level of the "Haus am See" the route turns west and runs for a length of approx. 300 m first in the asphalted residential street and then up to the transition to lot 3 in an agriculturally used arable land.
District heating extraction Stora Enso Lot 3Lot 3 comprises approx. 200 m.
Beginning and course of the route: The route of Lot 3 begins east of Raffineriestraße with the underpressure of Raffineriestraße towards the west.
From there, the route runs for a length of approx. 160 m in the direction of the Alb up to the level of the meeting place between people and dogs.