The Free and Hanseatic City of Hamburg intends to renew Königstraße between Max-Brauer-Allee and Reeperbahn, with a section of Veloroute 12, as part of the expansion of the cycle route network. The tendered services are to be carried out in Königstraße between Max-Brauer-Allee and Mörkenstraße. The road section has a length of about 0.7 km. In the process, the junctions or the junction areas Schillerstraße / Königstraße, Alte Königstraße / Königstraße, Biernatzkistraße / Professor-Brix-Weg / Königstraße, Behnstraße / Königstraße, Elmenhorststraße / Königstraße will also be constructed.
The main services are:
Bit. Upgrading the roadway 9,800 m²
Pick up and dispose of large pavements under asphalt 3,000 m²
Bit. Construction of the roadway in full expansion 8,300 m²
Making a mastic asphalt watercourse 400 m²
Pavement pavement, safety strip, cycle path 5,400 m²
Making parking stalls, crossings with honeycomb paving stones 550 m²
Making stops in concrete construction 240 m²
High curbs set 1,300 m
Setting low curbs 1,100 m
Adhesive curbs set 1,400 m
Bus special board set 38 m
Making a trumm connection cable 320 m
Making debris 65 pcs
Removing and recycling/disposing of soil, base courses 8,400 t
Preparing tree pits 30 pcs
The Free and Hanseatic City of Hamburg intends to renew Königstraße between Max-Brauer-Allee and Reeperbahn, with a section of Veloroute 12, as part of the expansion of the cycle route network. The tendered services are to be carried out in Königstraße between Max-Brauer-Allee and Mörkenstraße. The road section has a length of about 0.7 km. In the process, the junctions or the junction areas Schillerstraße / Königstraße, Alte Königstraße / Königstraße, Biernatzkistraße / Professor-Brix-Weg / Königstraße, Behnstraße / Königstraße, Elmenhorststraße / Königstraße will also be constructed.
The main services are:
Bit. Upgrading the roadway 9,800 m²
Pick up and dispose of large pavements under asphalt 3,000 m²
Bit. Construction of the roadway in full expansion 8,300 m²
Making a mastic asphalt watercourse 400 m²
Pavement pavement, safety strip, cycle path 5,400 m²
Making parking stalls, crossings with honeycomb paving stones 550 m²
Making stops in concrete construction 240 m²
High curbs set 1,300 m
Setting low curbs 1,100 m
Adhesive curbs set 1,400 m
Bus special board set 38 m
Making a trumm connection cable 320 m
Making debris 65 pcs
Removing and recycling/disposing of soil, base courses 8,400 t
Preparing tree pits 30 pcs