Description:
Retrofit CHP Project – Electrical Installation

Lifetime of the CHP project. Electrical Installation

• Demolition and scrapping of cables, drawers and cabinets, ducting, switchgear, power stations, transformers, lighting, etc.

• Delivery and installation of new lighting including switchgear, transformers, power stations, cabling, ducting, etc.

• Delivery and installation of new power and control cabling for process and new ducting

 

Time Sceduele

• The majority of all work will be performed over a period of 6 months more specific 2023-03-01 through 2023-08-31.

• Installation of lighting fixtures, including associated cabling, should be completed by 2023-12-31.

• Certain preparatory work will be carried out during the summer / autumn of 2022

 

Introduction

Stockholm Exergi AB (SE), is a provider of district heating, district cooling and electric power from a set of owned and operated plants and grid throughout the Stockholm metropolitan area. SE have taken an investment decision to invest in the lifetime extension of its largest combined heat and power plant (CHP) – KVV1 at – Värtaverket, in Stockholm.  

 

Project Description

The project objective is to extend the lifetime of the CHP with 25 years, to convert the systems for combustion of bio-oil and to reduce current levels of emissions to air. Original capacities and performance data, such as district heating and electrical production shall be achieved.

 

Scope

• Demolition and scrapping of cables, drawers and cabinets, ducting, switchgear, power stations, transformers, lighting, etc.

• Delivery and installation of new lighting including switchgear, transformers, power stations, cabling, ducting, etc.

• Delivery and installation of new power and control cabling for process and new ducting

 

Time Sceduele

• The majority of all work will be performed over a period of 6 months more specific 2023-03-01 through 2023-08-31.

• Installation of lighting fixtures, including associated cabling, should be completed by 2023-12-31.

• Certain preparatory work will be carried out during the summer / autumn of 2022, e.g. erection of a new switchgear for general power and lighting, supplementation with new ducting in the turbine hall, temporary electricity, etc.

 

Qulifiction Criterias

https://www.e-avrop.com/forumvarme/e-Upphandling/administration/Procurement.aspx?id=64758 (https://www.e-avrop.com/forumvarme/e-Upphandling/administration/Procurement.aspx?id=64758)

 

Download full details as .pdf
The Buyer:
Stockholm Exergi AB
CPV Code(s):
31200000 - Electricity distribution and control apparatus
31214000 - Switchgear
31600000 - Electrical equipment and apparatus
31682210 - Instrumentation and control equipment
45310000 - Electrical installation work
45316000 - Installation work of illumination and signalling systems
45317200 - Electrical installation work of transformers