Fire and rescue station 1 in the Hanseatic and University City of Rostock is to be renovated and expanded. The project is divided into 4 construction phases. The preparatory measures (repair, demolition, media supply) and the new construction of the control center building with disaster control warehouses and workshops will be implemented in the BA0+BA1 construction phases that are now being advertised and to be carried out.
The service includes in detail, among other things
Road construction - 1,300 m² concrete pavement
- 330 m² paving area
- 160 m Linienentwässerung DN 100/200
Pavement - 270 m² paving area
- Set 350 m grass board
- Make 30 m angle retaining wall
Sewer construction - 230 m lines DN 100/160/200
- 3 St Schacht, DN 400
- 5 St Regenwasserfilterschacht, DN 1000
Landscaping - 1,000 m² groundcover planting area