Construction logistics services for the overall Siko North Relocation Project Terminal 1B Frankfurt Airport (a total of 6 sub-projects on levels U1, E01, E02, E03) during ongoing operations: Establishment and operation of several construction site equipment, storage and unloading/loading areas (some with logistics containers, barriers, turnstile, storage tent, forklifts, waste disposal yard, magazine containers, construction elevator, transport walkway roof area) as well as area management of the construction site equipment areas. Receipt of deliveries, storage of materials, transport to the construction area with securing the transport routes within the terminal. Implementation of disposal logistics in the role of producer with documentation and polluter-pays billing. Establishment and operation of a notification system for deliveries as an Internet portal and a digitally readable construction site ID system with turnstile-controlled access.
Further information under II.2.4
Start of execution: approx. 2nd quarter 2024
Execution end date: approx. 3rd quarter 2027
Coarse mass extract:
Construction logistics with a duration of 182 weeks
- Storage area / handling area approx. 2,000 m², including 600 m² free storage space, storage tent approx. 500 m², 11 magazine containers
- Baustelleneinrichtungsfläche terminalnah ca. 1000 m²
- Transports from storage space to the construction area, Monday – Friday approx. 20 pallets per shift from 10:00 p.m. to 4:30 a.m., direct deliveries according to notification
- Telehandler
- 2 forklifts
- 4 sanitary containers
- 2 Logistikcontainer
- Entsorgungsmassen 2.800 m³