Civil engineering, track construction, platform construction, cable civil engineering
The call for tenders refers to the expansion of the Renningen and Weil der Stadt stations as well as the reopening of the Weil der Stadt - Calw section of the “Württemberg Schwarzwaldbahn” (line 4810) as a Hermann Hesse railway as well as the related superstructure and platform construction work in the stations Renningen and Weil der Stadt city.
1: Bf Renningen
new platform length approx. 55m; 55 cm a.s.so
railing approx. 85m
Track dismantling approx. 210m
Supply and installation rail about 535m
Supply and installation threshold approx. 455 pcs
turnout installation 3 pcs
superstructure base layer approx. 800 m²
Deliver and install crushed stone approx. 405 m³
soil disposal approx. 2,400 t
2: Bf Weil der Stadt
Platform dismantling incl. loading ramp length approx. 50m; approx. 650 m²
new platform length approx. 55m; 55 cm a.s.so
Track dismantling approx. 70m
Supply and installation rail approx. 140m
Supply and installation threshold approx. 115 pcs
soil disposal approx. 600 t
3: railway/level crossing
Track dismantling approx. 1,180 m
New construction track 1,640 m
Gravel excavation approx. 5,380 t
Earth excavation approx. 2,000 m³
soil improvement approx. 2,725 m³
New building Randweg approx. 1,545 m
new cable duct approx. 1,640 m
Reprofiling moat approx. 1,130 m
Deep drainage renewal approx. 230 m
asphalt work approx. 100 m2
reinforced concrete track plates approx. 20 m2