Power installations.
- 1 piece of UPS 80 kVA,
- 1 piece partial renewal power supply system,
- 5 pieces low-voltage switch cabinets,
- 1 piece performance optimization system,
- 52 pieces of subdivisions,
- 2 500 pieces of installation equipment,
- 1 500 m cable tray,
- 62 pieces of floor tanks,
- 55 000 m installation cable up to 5 x 2.5 mm
- 1 500 m to 5 x 35 mm
- 420 m 4 x 150 mm
- 1 piece lighting system with 525 m strip lights,
- 22 pieces of light figures,
- 300 pieces of emergency lighting system with 12 emergency lighting units 24 V and 225 pieces of office lighting of different lengths,
- 2 pieces of light ceilings approx. 3x2 m,
- 49 pieces of ring lights,
- 250 pieces of moisture-proof lights,
- 127 pieces of emergency number lights,
- 20 pieces of group battery systems,
- 25 pieces of pole lights,
- 1 lightning protection system with arresters and separation boxes,
- 220 m catch line.