Addition and restoration of historic ceiling stucco areas including connections to wall surfaces and cornices as well as preparatory work on plaster and substructure
S-391 Stuck BT. B, C, D
Addition and restoration of historic ceiling stucco areas including connections to wall surfaces, cornices and preparatory work on plaster and substructure
Stucco:
- 1659 m² gypsum plaster on ceilings and walls
- 377 m² Manufacture substructure wood
- 377 m² Neuherstellen Stuck
- 405 m² Revise stucco
Construction of the trade is scheduled to begin in week 30 2023. The construction process will be staggered according to components, with stucco completion by 30 week 2024.
Staggered journeys are required for the provision of services.
The client reserves the right to award the advertised services or parts of the advertised services.