Brothers of Mercy, Hospital St. Barbara Schwandorf - Masterplan 1.BA//5010 Outdoor Facilities Quantities Main works:
- demolition of asphalt surfaces approx. 60 to,
- demolition pavement areas about 680 m
- Demolition natural stone wall approx. 300 m³,
- Asphalt surfaces approx. 4 580 m
- Paving about 1 800 m
- Grass area approx. 520 m
- Planting area about 3 400 m
- lawn honeycomb about 220 m
Start of execution: Immediately after the order is placed, approx. KW 30 - 22.7.2019.
End of execution: expected approx. KW 44 - 31.10.2019.
Brothers of Mercy, Hospital St. Barbara Schwandorf - Masterplan 1.BA 5010 Outdoor Facilities Quantities of the main works:
- demolition of asphalt surfaces approx. 60 to,
- demolition pavement areas about 680 m
- Demolition natural stone wall approx. 300 m³,
- Asphalt surfaces approx. 4 580 m
- Paving about 1 800 m
- Grass area approx. 520 m
- Planting area about 3 400 m
- lawn honeycomb about 220 m
Period:
Start: Immediately after the order is placed, approx. CW 30 - 22.7.2019.
End of execution: expected approx. KW 44 - 31.10.2019.