Lot 11 Carpentry/interior door work
BV: Reconstruction and renovation of the Alte Post Leuna
Lot 11 Carpentry and interior door work
The client, the housing industry Leuna GmbH, intends to extensively renovate and renovate the residential building. There are 31 low-barrier apartments on 3 floors (1.BOG/2.OG/ DG) and 6 commercial units on the ground floor.
The building is accessed via 2 stairwells, each with attached elevators. On the residential floors, the residential units are accessed via an internal corridor.
The building is located in the area of a designated area monument of the city of Leuna.
The work is planned in 6 phases, so that the building envelope and the roof construction (roof truss) can remain during the conversion work. It is not possible to work continuously in all construction phases at the same time.
The execution will take place in 6 construction phases. The separation takes place at the former house entrances / staircases. All work is carried out with slight offset. It is therefore to be expected with several approaches according to the construction schedule.
- 27 pieces sliding door incl. drive and cover for wooden doors 1-flg
- 96 pieces interior doors incl. enclosure door frame for wooden doors 1-flg
- 32 pieces apartment entrance door (37dB) 1-flg
- 2 pieces sliding door incl. drive and cover for wooden doors 2-flg