The client is planning to set up an NGA network (FTTB) on part of the municipal area of the municipalities of Pfaffenweiler and Schallstadt. The aim is to eliminate any white spots that still exist there.
Lot 1 PfaffenweilerThe Zweckverband Breitband Breisgau-Hochschwarzwald (client) comprises 40 cities and municipalities in the district of Breisgau-Hochschwarzwald as well as the district of Breisgau-Hochschwarzwald itself.
The task of the special-purpose association is to ensure an expansion with fiber optics for underserved households and commercial enterprises in the association area.
In the context of a previous Europe-wide tender, an operator for subsequent grid operation was identified via the special-purpose association. Vodafone GmbH, which has been selected as the network operator, will operate the client's planned network for expansion.
The client plans to build an NGA network (FTTB) within part of the municipal area of the Verbandsgemeinde of Pfaffenweiler. The aim is to eliminate any white spots that are still present there.
The project is to be funded according to the guideline "Funding to support broadband expansion in the Federal Republic of Germany" as well as according to the administrative regulation of the Ministry of the Interior for co-financing the funding from the guideline for the support of broadband expansion in the Federal Republic of Germany (VwV broadband co-financing) and VWV broadband funding. The preliminary funding decision of 02.08.2021 for the project is attached in the attachment preliminary funding decision of 02.08.2021. Overall, investments totalling around EUR 830,726.41 net are planned for the expansion of the NGA network (FTTB).
The specifications and specifications of the funding or project promoter regarding the material concept must be observed.
Investments of around EUR 1,078,000.00 net are planned for the expansion of the backbone.
Planning status Pfaffenweiler
The listed route lengths can be reduced or shifted due to co-laying that has been coordinated in the meantime.
Backbone
State Broadband Funding File number: will be submitted later
- Construction of new route (paved surface): 3,125 m
- New line construction (unpaved surface): 2,265 m
- Shafts: 6 pcs.
Local network
Federal Broadband Funding e-file number: 823.5/3-2009BW200634
The current planning status corresponds to a design planning based on the existing structural planning. A total of approx. 25 FTTB house connections are planned. The project comprises:
- Construction of new railway line (paved surface): 1,731 m
- FTTB distributors (cabinets and/or shafts): 5 pieces
- POP prefabricated buildings and/or cabinets: 1 piece
Furthermore, the eligible drivage based on reserve capacities and the connection of paths of adjacent light grey spots (excluding tunnelling addresses) via the grey spots upgrade are planned. Further strategic-functional connections in the context of the upgrade grey spots are reserved.
The planning status will be communicated accordingly with the request to submit an offer in the next procedural step.
Everything else can be found in the appendix task description to the tender documents, to which reference is made in full.
Lot 2 SchallstadtThe Zweckverband Breitband Breisgau-Hochschwarzwald (client) comprises 40 cities and municipalities in the district of Breisgau-Hochschwarzwald as well as the district of Breisgau-Hochschwarzwald itself.
The task of the special-purpose association is to ensure an expansion with fiber optics for underserved households and commercial enterprises in the association area.
In the context of a previous Europe-wide tender, an operator for subsequent grid operation was identified via the special-purpose association. Vodafone GmbH, which has been selected as the network operator, will operate the client's planned network for expansion.
The client plans to build an NGA network (FTTB) within part of the municipal area of Schallstadt. The aim is to eliminate any white spots that are still present there.
The project is to be funded according to the guideline "Funding to support broadband expansion in the Federal Republic of Germany" as well as according to the administrative regulation of the Ministry of the Interior for co-financing the funding from the guideline for the support of broadband expansion in the Federal Republic of Germany (VwV broadband co-financing) and VWV broadband funding. The preliminary funding decision of 26.04.2021 for the project is attached in the attachment preliminary funding decision of 26.04.2021. Overall, investments totalling around EUR 1,725,182.83 net are planned for the expansion of the NGA network (FTTB).
The specifications and specifications of the funding or project promoter regarding the material concept must be observed.
Investments of around EUR 2,578,600.00 net are planned for the expansion of the backbone.
Planning status Schallstadt
The listed route lengths can be reduced or shifted due to co-laying that has been coordinated in the meantime.
Backbone
State Broadband Funding File number: will be submitted later
- New line construction (paved surface): 7,872 m
- New line construction (unpaved surface): 5,021 m
- Shafts: 12 pcs.
Local network
Federal Broadband Funding e-file number: 823.5/3-2109BW200696
The current planning status corresponds to a design planning based on the existing structural planning. A total of approx. 57 FTTB house connections are planned. The project comprises:
- Construction of new route (paved surface): 4,034 m
- FTTB distributors (cabinets and/or bays): 8 pieces
- POP prefabricated buildings and/or cabinets: 2 pieces
Furthermore, the eligible drivage based on reserve capacities and the connection of paths of adjacent light grey spots (excluding tunnelling addresses) via the grey spots upgrade are planned. Further strategic-functional connections in the context of the upgrade grey spots are reserved.
The planning status will be communicated accordingly with the request to submit an offer in the next procedural step.
Everything else can be found in the appendix task description to the tender documents, to which reference is made in full.
Lot 3 EbringenThe Zweckverband Breitband Breisgau-Hochschwarzwald (client) comprises 40 cities and municipalities in the district of Breisgau-Hochschwarzwald as well as the district of Breisgau-Hochschwarzwald itself.
The task of the special-purpose association is to ensure an expansion with fiber optics for underserved households and commercial enterprises in the association area.
In the context of a previous Europe-wide tender, an operator for subsequent grid operation was identified via the special-purpose association. Vodafone GmbH, which has been selected as the network operator, will operate the client's planned network for expansion.
The contracting authority plans to build an NGA network (FTTB) within part of the boundaries of the Verbandsgemeinde of Ebringen. The aim is to eliminate any white spots that are still present there.
The project is to be funded according to the guideline "Funding to support broadband expansion in the Federal Republic of Germany" as well as according to the administrative regulation of the Ministry of the Interior for co-financing the funding from the guideline for the support of broadband expansion in the Federal Republic of Germany (VwV broadband co-financing) and VWV broadband funding. The preliminary funding decision of 26.07.2021 for the project is attached to the provisional funding decision of 26.07.2021. Overall, investments totalling around EUR 2,618,038.56 net are planned for the expansion of the NGA network (FTTB).
The specifications and specifications of the funding or project promoter regarding the material concept must be observed.
Investments of around EUR 976,000.00 net are planned for the backbone.
Planning status Ebringen
The listed route lengths can be reduced or shifted due to co-laying that has been coordinated in the meantime.
Backbone
State Broadband Funding File number: will be submitted later
- Construction of new railway line (paved surface): 3,507 m
- New line construction (unpaved surface): 1,373 m
- Shafts: 5 pcs.
Local network
Federal Broadband Funding e-file number: 823.5/3-2009BW200635
The current planning status corresponds to a design planning based on the existing structural planning. A total of approx. 36 FTTB house connections are planned. The project comprises:
- New route (paved surface): 7,223 m
- FTTB distributors (cabinets and/or bays): 17 pieces
- POP prefabricated buildings and/or cabinets: 1 piece
Furthermore, the eligible drivage based on reserve capacities and the connection of paths of adjacent light grey spots (excluding tunnelling addresses) via the grey spots upgrade are planned. Further strategic-functional connections in the context of the upgrade grey spots are reserved.
The planning status will be communicated accordingly with the request to submit an offer in the next procedural step.
Everything else can be found in the appendix task description to the tender documents, to which reference is made in full.