Modernization and renovation of the Löweneck elementary and middle school with integrated gyms in Oberhausen.
The school will be modernized in 4 phases.
The fire alarm systems contained in the school apply in relation to the fire protection certificate on K1 full protection for expansion / renewal, in this regard the following main positions are listed with approx. Information:
- Loop extensions 6 pieces,
- Exchange batteries 4 pieces,
- Display control panel 1 piece,
- surge protection 20 pieces,
- Linking an existing FIZ, FSD, FES,
- detector heaters 31 pieces,
- Optical detectors 170 pieces,
- Automatic detectors 328 pieces,
- 58 non-automatic detectors,
- ring bus siren 197 pieces,
- fire brigade ladders 12 pieces,
- BMA signage,
- disassembly and storage of existing detectors approx. 100 pieces,
- Disassembly and disposal of detectors approx. 430 BMA components.
Modernization and renovation of the Löweneck elementary and middle school with integrated gyms in Oberhausen.
The school will be modernized in 4 phases.
The fire alarm systems contained in the school apply in relation to the fire protection certificate on K1 full protection for expansion / renewal, in this regard the following main positions are listed with approx. Information:
- Loop extensions 6 pieces,
- Exchange batteries 4 pieces,
- Display control panel 1 piece,
- surge protection 20 pieces,
- Linking an existing FIZ, FSD, FES,
- detector heaters 31 pieces,
- Optical detectors 170 pieces,
- Automatic detectors 328 pieces,
- 58 non-automatic detectors,
- ring bus siren 197 pieces,
- fire brigade ladders 12 pieces,
- BMA signage,
- disassembly and storage of existing detectors approx. 100 pieces,
- Disassembly and disposal of detectors approx. 430 BMA components.