As part of an appointment of the Research Alliance Ruhr, a new laser/accelerator laboratory is to be set up in the test hall of DELTA (Dortmund ELekTronenspecherring facility), which is independent of the existing 1,5-GeV electron storage ring, which is located at the Technical University of Dortmund by the Center for Synchrotron
The aim of the construction project is the creation of a new laser laboratory/accelerator laboratory in the DELTA hall, at the Center for Synchrotron Radiation in Maria-Goeppert-Mayer-Str. 2 through new construction and conversion of the existing building. The planning of the construction project is to be awarded as a general planning service in the course of this award procedure.
Planning phase LPH 1 to LPH 4:
December 2023 - April 2024
Completion of design planning:
March 2024
Planning phase LPH 5 to LPH 6:
May 2024 - July 2024
Conclusion Preparation of the award:
July 2024
Awarding and construction LPH 7 to LPH 8:
August 2024 - April 2025
Handing over to users:
May 2025
Regulations for step-by-step commissioning
With the conclusion of the contract, the client transfers the services according to 4.1.2 (contract) to the contractor.
If the planning and execution of the construction project continues, the client intends to call up further services in accordance with § 4 numbers 4.2 to 4.3. The retrieval takes place in text form